most citedDifferent Cost Performance: Different Determinants? The Case of Cost Overruns in Dutch Transportation Infrastructure Projects

182 citations · 434 across the 3 of their papers we have counts for

collaborators

4 papers

q-fin.GN2013★ 106 cited

Lock-in and Its Influence on the Project Performance of Large-Scale Transportation Infrastructure Projects. Investigating the Way in Which Lock-in Can Emerge and Affect Cost Overruns

Chantal C. Cantarelli, Bent Flybjerg, Bert van Wee +1

Lock-in, the escalating commitment of decision-makers to an ineffective course of action, has the potential to explain the large cost overruns in large scale transportation infrast…

q-fin.GN2013

Cost overruns in Large-Scale Transportation Infrastructure Projects: Explanations and Their Theoretical Embeddedness

Chantal C. Cantarelli, Bent Flybjerg, Eric J. E. Molin +1

Managing large-scale transportation infrastructure projects is difficult due to frequent misinformation about the costs which results in large cost overruns that often threaten the…

q-fin.GN2013★ 182 cited

Different Cost Performance: Different Determinants? The Case of Cost Overruns in Dutch Transportation Infrastructure Projects

Chantal C. Cantarelli, Bert van Wee, Eric J. E. Molin +1

This paper examines three independent explanatory variables and their relation with cost overrun in order to decide whether this is different for Dutch infrastructure projects comp…

q-fin.GN2013★ 146 cited

Characteristics of Cost Overruns for Dutch Transport Infrastructure Projects and the Importance of the Decision to Build and Project Phases

Chantal C. Cantarelli, Eric J. E. Molin, Bert van Wee +1

Using a methodology similar to that used the in the worldwide research, the cost performance of Dutch large-scale transport infrastructure projects is determined. In the Netherland…